11/02/2026

Agua Fría Wastewater Project Phase 3 begins

SANTA FE, N.M., Nov. 2, 2026—Santa Fe County is beginning phase three of the Agua Fría Wastewater Project, a five-phase project, with phases one and two completed. Staging for construction has already begun, and message boards are being placed in the area to notify residents of the upcoming work.

Construction begins this month and continues through summer of 2027. Residents on affected streets will be contacted prior to construction.

This project is funded by New Mexico Environment Department grants to provide sewer infrastructure to the residents in the Agua Fría Village so that they can connect to these services rather than using failing and outdated septic systems. Once completed, the project will service 37 streets.

Phase three will cover ten streets: Avenida De Sesario, Alamo Lane, Lopez Lane, 3945 Agua Fría Street, Ledd Drive, Camino dos Antonios, Cellejon De Rita, Plaza Montoya, Case Road, 3917 Agua Fría Street, Skeeter Lane.

The map of the streets and the proposed schedule of work are below. All dates and the order of construction are subject to change.

Street where work will take place

Approximate start Approximate end
Callejon de Rita Nov. 4, 2026 Jan. 2027
Avenida de Sesario Nov. 4, 2026 Jan. 2027
Alamo Lane Jan. 2027 March 2027
Ledd Drive Jan. 2027 Feb. 2027
Callejon de Rita sewer line testing and construction zone resurfacing Feb. 2027 Feb. 2027
Camino dos Antonios Feb. 2027 March 2027
Lopez Lane  March 2027 May 2027
Case Road March 2027 April 2027
Alamo Lane sewer line testing and construction zone resurfacing April 2027 April 2027
3197 Agua Fría April 2027 April 2027
Plaza Montoya April 2027 May 2027
Skeeter Lane May 2027 May 2027
Lopez Lane sewer line testing and construction zone resurfacing June 2027 June 2027
Plaza Montoya sewer line testing and construction zone resurfacing June 2027 June 2027
Skeeter Lane sewer line testing and construction zone resurfacing June 2027 July 2027

####