11/02/2026
Agua Fría Wastewater Project Phase 3 begins

SANTA FE, N.M., Nov. 2, 2026—Santa Fe County is beginning phase three of the Agua Fría Wastewater Project, a five-phase project, with phases one and two completed. Staging for construction has already begun, and message boards are being placed in the area to notify residents of the upcoming work.
Construction begins this month and continues through summer of 2027. Residents on affected streets will be contacted prior to construction.
This project is funded by New Mexico Environment Department grants to provide sewer infrastructure to the residents in the Agua Fría Village so that they can connect to these services rather than using failing and outdated septic systems. Once completed, the project will service 37 streets.
Phase three will cover ten streets: Avenida De Sesario, Alamo Lane, Lopez Lane, 3945 Agua Fría Street, Ledd Drive, Camino dos Antonios, Cellejon De Rita, Plaza Montoya, Case Road, 3917 Agua Fría Street, Skeeter Lane.
The map of the streets and the proposed schedule of work are below. All dates and the order of construction are subject to change.
|
Street where work will take place |
Approximate start | Approximate end |
| Callejon de Rita | Nov. 4, 2026 | Jan. 2027 |
| Avenida de Sesario | Nov. 4, 2026 | Jan. 2027 |
| Alamo Lane | Jan. 2027 | March 2027 |
| Ledd Drive | Jan. 2027 | Feb. 2027 |
| Callejon de Rita sewer line testing and construction zone resurfacing | Feb. 2027 | Feb. 2027 |
| Camino dos Antonios | Feb. 2027 | March 2027 |
| Lopez Lane | March 2027 | May 2027 |
| Case Road | March 2027 | April 2027 |
| Alamo Lane sewer line testing and construction zone resurfacing | April 2027 | April 2027 |
| 3197 Agua Fría | April 2027 | April 2027 |
| Plaza Montoya | April 2027 | May 2027 |
| Skeeter Lane | May 2027 | May 2027 |
| Lopez Lane sewer line testing and construction zone resurfacing | June 2027 | June 2027 |
| Plaza Montoya sewer line testing and construction zone resurfacing | June 2027 | June 2027 |
| Skeeter Lane sewer line testing and construction zone resurfacing | June 2027 | July 2027 |
####