Avenida del Sur road extension updates and road closure
SANTA FE, N.M., May 18, 2026—Construction on the road extensions for Avenida del Sur and College Drive in Santa Fe County continues, with an upcoming road closure for part of Avenida del Sur. Once completed, the new roadways will provide critical connections to existing roads to support current neighborhoods and future development.
There will be a road closure at the intersection of Avenida del Sur and A Van Nu Po beginning May 26 through the end of July, for construction of a roundabout at the intersection of these streets, and other upgrades. Those trying to reach A Van Nu Po from Avenida del Sur will need to detour using Richards Avenue, and those trying to reach Avenida del Sur from A Van Nu Po will also need to detour using Richards Avenue (see map). There will be signage alerting drivers to the closure.
Construction on College Drive began mid-February with installation of a new waterline. The College Drive section is nearing completion, with final waterline installation and paving of the road and trail in the coming weeks. The road should be substantially complete in early June.
Construction began on the Avenida del Sur extension mid-March and will continue in three phases. The project is expected to be finished by mid-December this year, although utility issues or property acquisition could cause delays. Construction is currently in Phase 1, at the entry to the newly developed Esencia property at the intersection of Via Esencia, and east to the intersection of A Van Nu Po, and includes construction of a roundabout at each of those intersections. The timeline for this work depends on utility relocations and in-progress property acquisitions.
Phase two will address the existing, unpaved section of Vista Del Monte beginning at the Via Esencia roundabout on the east and ending at the start of the paved portion of Avenida Del Sur on the west.
Phase two includes property acquisition to extend the road right-of-way an additional 30 feet to the north to accommodate a sidewalk, 11- to 12-foot driving lanes, bike lanes in both directions, and reinforced drainage. Retaining walls will be installed where necessary and utility relocations will be required. Any disruptions to service should be minor, and the County will communicate with affected property owners.
The major work of phase two will begin once all property acquisition negotiations are completed. Utility relocations have already begun and will continue through the summer.
Phase three will be a mill and overlay of the existing section of paved roadway on Avenida Del Sur. This will begin at the edge of the new paving project and end at the intersection with NM-14 and NM-599. There will be no changes to the road width in this section.
The extensions are key components of Santa Fe County’s long-range planning for the Rancho Viejo Area, helping to balance the demand for new growth close to existing infrastructure in the vicinity of Santa Fe Community College. The road projects are collaborations between Santa Fe County and adjacent land development projects and will be constructed under a single contractor managed by the County.
Throughout the project, the County will continue with outreach to area residents and businesses that began in June 2025.
####